
This article was written by Sarah Bacha for use in
construction digest.
. . . . . . . Late last
fall, a multi-company team led by EXXCEL Contract Management
Inc., a Columbus-based general contracting construction firm, set
out to pour a concrete floor at an industrial park in Louisville,
Ky. End of story. Or so officials at EXXCEL thought.
. . . . . . . Little did they know that bad weather
would hamper the project at about the time soon-to-be tenant,
Valley Record Distributors, accelerated its planned move-in date.
Despite these obstacles and others, the 225-person crew beat the
odds and accomplished its mission, while at the same time setting
what is believed to be a world record for the largest continuous
pouring of a flat concrete surface last November.
. . . . . . . 'It was a classic example of team work.'
said Rick Warren, project chief for EXXCEL. "By working
together, we were able to respond to the challenges head-on and
overcome them."
. . . . . . . The story leading up to the pour went
like this:
. . . . . . . On Thursday, Oct. 30, 1997, the company
began pouring the floor of the approximately 300,000 square-foot
building. Only 31,000) square feet was poured before rains and
accompanying fog related to El Nino stopped the project.
. . . . . . . "The fog was so intense that the
lasers on equipment couldn't work, and the weather forecast
showed no improvement," said Mike McBrayer, site contract
manager for EXXCEL.
. . . . . . . Time was running out. Warren, McBrayer,
and their team decided that Saturday, Nov. 8, 1997, would be the
day to pour the remaining 270,000 square-feet of concrete. It was
the only day that four batch plants could be coordinated to
supply the volume of concrete needed, no small feat in itself. A
slight break in the weather was predicted to occur as well.
. . . . . . . "We had four concrete batch plants
and two concrete companies involved in the pour, as well as a
geotechnical engineering firm." said Warren, who was in
charge of overseeing logistics. Also scheduled to be used were:
86 concrete trucks: 18 double-trowel machines; four laser
screeds; 24 light plant systems; two small bulldozers; two smooth
drum rollers; and four 42-meter concrete pumps.
. . . . . . . Some of the materials and equipment were
traveling from as far away as Columbus. The team's war room
contained 16 pages of checklists that covered even the most
minute detail, such as what each semi was carrying and its
estimated time of arrival.
. . . . . . . As EXXCEL finalized arrangements the
week before, rain continued to be a problem. That meant the
sub-base was too wet, which required additional work to prepare
for the pour. That also meant that the sub-base couldn't support
trucks, requiring that the concrete had to be pumped.
. . . . . . . D-Day arrived. "It rained up until
10 minutes before we were ready to begin." Warren recalled.
In the early morning hours, the crew began placing the concrete
and hoped the rain would hold off. It did. And during the day,
the sun actually came out, while the temperature stayed at about
40 degrees Fahrenheit.
. . . . . . . Some 30 hours later, the crew smoothed
out the last patch of concrete end covered it with plastic.
Within minutes, the rain returned.
. . . . . . . In the end, the EXXCEL team used 396
trowel blades and $12,000 worth of plastic covering. More
importantly, the work surpassed industry standards. Concrete
yields were within 2 percent of calculated quantities and less
than estimated quantities. The floor flatness was a Ff. 54.60 and
levelness was a Fl 43.83. By comparison, the industry standard
for floor flatness is 35.
. . . . . . . And the team received notice, much to
its surprise, that it had set what is believed to be a world
record for the largest square footage of a flat surface ever
poured at one time.
. . . . . . . According to industry expert, George
Haming, sales manager for Garceveur Corp., Louisville, the
previous record for a flat area being poured is believed to be
250,000 square feet. That pour occurred last spring in Alabama.
The EXXCEL pour was praised for maintaining such high flatness
and levelness. "Those are fantastic numbers for a project
that large. Haming said. While the cubic volume poured - 5,021
cubic yards - may be considered small when compared with other
large pours, Haming said what sets this project span Is that the
team maintained such consistency over a large, flat area. 'It's
much easier to pour concrete into a big hole,' he said.
. . . . . . . "What's unique about this project
if that a typical pour of this size would have occurred over
multiple days. EXXCEL basically compressed about seven working
days into 30 hours," said James Miller, senior vice
president of development for Columbus, Ohio-based Pizzuti
Development. Pizzuti developed the warehouse for Valley Record
Distributors at the Riverport industrial Park.
. . . . . . . "We've worked with EXXCEL for many
years and have a high level of trust and confidence in the
company," Miller said. "EXXCEL is known for its
construction of quality floors and for working with some of the
best flat work subcontractors in the industry, We trust their
recommendations, because we know they are dealing with the
experts."
. . . . . . . The building is expected to be completed
in May and, thanks to EXXCEL's efforts, the project is on target
to meet the client's accelerated schedule, Pizzuti's Miller said.
. . . . . . . "In our view, when it comes to
these kinds of projects, we have a big commitment to meet our
customers' needs, That means being innovative and trying to
identify and create solutions that win for everybody. EXXCEL
follows this philosophy, too." Miller said.
. . . . . . . Reflecting back on the pour, Warren
said, "We didn't set out to break any records; we just had a
job to complete. He expects the record will likely be short-lived
as construction schedules become tighter and technological
advancements become available.
. . . . . . . Warren and McBrayer said that what
impressed them the most was the team spirit that prevailed during
the pour, Workers representing four companies were involved:
Lithko Contracting, Columbus; T & C Excavating, Louisville:
AML Inc., Floyds Knobs, Ind. and IMI Concrete, Louisville. Warren
had particular praise for Lithko. "Without their help and
willingness to go the extra mile, the pour would not have been
possible"
. . . . . . . The team spirit was so high that crews
did not want to leave the site when their shift was finished,
Warren said. By the end, all shifts were still working. "In
all my years of construction work, I haven't seen anything quite
like it."
|